HIGHEST, LOWEST, AND TOTAL UK PRICE FOR REQUIRED PRODUCTS AND SERVICES
These prices are a result of research into the UK pricing market for building construction and are factual. The document shows the highest and lowest prices that could be found using conventional research methods. The areas or quantities have been included, and the totals are for both the highest and lowest prices. This section of the document only covers building materials.
The remainder of the document will show two options, ‘A’ and ‘B’. All materials and services are included in option ‘A’, and this reflects the total cost to completion. In option ‘B’, which uses an alternate contractor for the steel construction, they are removed when deemed not required. The totals also represent these omissions. These prices are not fixed and will change in either direction when quotes or local research are applied. The object is to give the reader a realistic picture of what the total finished building will cost.
What is required, how much do we need, and what will it cost for each product?
| Products - Services - Quantities | Lowest | Highest | |
|---|---|---|---|
| Part Wall Agreement | £770 | £5000 | |
| Demolition | £8000 | £12000 | |
| Heras Safety Fencing | £783 | £783 | |
| HSE Portaloo - per week | £30 | £70 | |
| Soil Pipe 15mt,3 sealed gullys, 3 pan connections | £6150 | £9300 | |
| Site office per week for second hand shipping container 20ft x 8ft | £35 | £55 | |
| Provide drawings for building control and building regulations | £3600 | £8000 | |
| Building Control Fees | £900 | £1200 | |
| Supply and fit - 0.9mt x 0.6mt x Trench filled footing 900mm deep x 600mm wide x 29mt length, Volume: 29m × 0.9m × 0.6m = 15.66m³ Estimated Cost: Approximately per linear metre, - totalling £4,350–£7,250 | £4350 | £7250 | |
| Supply and fit – and Beam concrete floor 102 square meters, Estimated Cost: £200–£250 per m² - Total: £20,400–£25,500 | £20400 | £25000 | |
| Provide Light Guage Steel building frame to wrapped stage | £66278 | £95000 | |
| Supply and fit - 68 square meters of new roof with OSB board, roofing felt, tile battens and metal roof tiles, Estimated Cost: £120–£230 per m². | £8160 | £15640 | |
| Supply and fit - Brick Cladding 134 square meters, Estimated Cost: £35–£100 per m² . | £4690 | £13040 | |
| Supply and fit - Timber Cladding 134 square meters, Estimated Cost: £30–£70 per m². | £4020 | £9380 | |
| Supply and fit 34 mts of PVC gutter and 24 mts of downpipe. Price per meter for gutter £35-£45. Price per meter for down pipe £35-£45 per meter. | £2380 | £3060 | |
| Supply and fit - 30 square meters of Aluminium Double Glazing, Estimated Cost: £500–£650 per m². | £15000 | £19000 | |
| Supply and fit – sanitary ware for Men’s, Ladies and disabled toilets and kitchen sink with water heater, kitchen unit and work top. | £2325 | £4450 | |
| Supply and Fit – Air Source heat pump and radiators (Floor area 102 square meters, Estimated Cost: £11,000–£20,000 before grants. Government Grant: Up to £7,500 available through the Boiler Upgrade Scheme (This won’t apply, but there could be a charity angle) - Total After Grant: £3,500–£12,500 | £3500 | £12500 | |
| Supply and fit – 15 1mt x 1mt safety grilles for windows. | £7500 | £12750 | |
| Supply and Fit 420 m2 of foil backed polyurethane insulation board at 100mm thickness: Total. | £16800 | £21000 | |
| Supply and fit 85 m2 of Cement Screed at 50mm | £1530 | £2295 | |
| Electrical Installation Costs Using a 3-bedroom house as a model Average Cost: Approximately £6,255. Typical Range: Between £4,450 and £8,000, | £6255 | £8000 | |
| Plumbing Installation Costs Using a 3-bedroom house with two bathrooms as a model Average Cost: Approximately £19,000. Typical Range: Between £17,000 and £21,000, influenced by factors like fixture quality and property layout. | £17000 | £21000 | |
| Supply and fit 358 Square meters of Plasterboard and plaster skim £25–£45 per m2 | £8950 | £16110 | |
| Supply and fit 102 square meters of Heavy-duty floor covering costs between £20 and £60 per square meter. | £2040 | £6120 | |
| Decorating with undercoat, gloss, and emulsion. | £3000 | £6000 | |
The table below shows Option ‘A’. This shows everything that would be required from start to finish assuming that we handed the whole project over to someone to manage the construction on our behalf.
| Option A | |||
|---|---|---|---|
| Product | Lowest | Highest | Average |
| Party Wall Agreement/Award | 770 | 5000 | 3620 |
| LGS Construction, including design | 90000 | 95000 | 92500 |
| Building Control Services (Mark) | 1266 | 1266 | 1266 |
| Drawings for Building Control and Building Regulations | 3600 | 8000 | 5800 |
| Heras Safety Fencing | 784 | 784 | 784 |
| Site office | 8000 | 12000 | 10000 |
| Demolition | 8000 | 12000 | 10000 |
| Portaloo per week | 30 | 70 | 50 |
| Soil Pipe 15mt,3 sealed gulleys, 3 pan connections | 6150 | 9300 | 7725 |
| Supply and fit 102 square meters of Heavy-duty floor | |||
| Footings | 4350 | 7250 | 5800 |
| Sub Floor | 20400 | 25500 | 22950 |
| Cement Screed st 50mm thickness | 1530 | 2295 | 1933 |
| Scaffolding (Erection) | 5370 | 8950 | 7160 |
| Scaffolding (on going hire over 12 months) | 3900 | 7800 | 5850 |
| Roofing | 8160 | 15640 | 11900 |
| Guttering and Downpipes | 2380 | 3060 | 2720 |
| Brick Cladding | 4690 | 13400 | 9045 |
| Polyurethane Foil Backed insulation board at 100mm thickness | 16800 | 21000 | 18900 |
| Timber Cladding | 4020 | 9380 | 6700 |
| Aluminium Double Glazing | 15000 | 19500 | 17250 |
| Saniary ware (Ladies, Mens, Disabled) | 6500 | 9500 | 8000 |
| Supply + Fit 12 window boards, 5 internal doors, 5 sets of door furniture, 100mt of 150mm x 18mm skirting board | 2890 | 5070 | 3980 |
| Air Soiurce Heat Pump | 11000 | 20000 | 15500 |
| Internal Plaster Board and Skim | 8950 | 12530 | 10740 |
| Saftey Grills | 7500 | 12750 | 10125 |
| Eclectricals | 4500 | 8000 | 6250 |
| Plumbing (Supply and Fit) 2x wc pans, 1x Disabled pan, 3 x hand basins, 1 x Kitchen sink | 6500 | 9500 | 8000 |
| Sloar Panels | 7000 | 9800 | 8400 |
| Total | £263,202,00 | £371,995,00 | £317,734,00 |
| Project Management (average 15%) | 30505 | 50842 | 40673 |
| Total including Project Mangement | £293,707,00 | £422,837,00 | £358,407,00 |
This table shows Option ‘B’. By changing the contractor for the LGS structure has resulted in a number of the services being amalgamated into the new quote and this has had a significant a significant impact on the overall cost
| Option B | |||
|---|---|---|---|
| Product | Average | NOTES | |
| Party Wall Agreement/Award | 3620 | Maybe required, maybe a local agreement can be obtained. | |
| JPSE | 66278 | Quote Received | |
| Building Control Services (Mark) | 1266 | Quote received | |
| Drawings for Building Control and Building Regulations | 5800 | Trustees to arrange | |
| Heras Safety Fencing | 784 | From Internet Search | |
| Site office | Site Office.(Asgard Secure Steel Shed). This building is recomended by the Police. | ||
| Demolition | 10000 | Contractor on hold | |
| Portaloo per week | 50 | Quote Requested | |
| Soil Pipe 15mt,3 sealed gulleys, 3 pan connections | 7725 | Trustees to arrange | |
| Footings | Not reqd for main structure. JPSE construct from inside | ||
| Sub Floor | Required for timber cladding, guttering ect | ||
| Cement Screed st 50mm thickness | 1933 | Scaffold maybe supplied by roofing contractor within quote. If not, may require addition rental for externals | |
| Scaffolding (Erection) | 7160 | Trustees to arrange contractor | |
| Roofing | 11900 | Trustees to arrange contractor | |
| Guttering and Downpipes | 2720 | Trustees to arrange contractor | |
| Brick Cladding | 9045 | Trustees to arrange contractor | |
| Polyurethane Foil Backed insulation board at 100mm thickness | 18900 | Trustees to arrange contractor | |
| Timber Cladding | 6700 | Trustees to arrange contractor | |
| Aluminium Double Glazing | 17250 | Trustees to arrange contractor | |
| Saniary ware (Ladies, Mens, Disabled) | 8000 | Trustees to arrange contractor | |
| Supply + Fit 12 window boards, 5 internal doors, 5 sets of door furniture, 100mt of 150mm x 18mm skirting board | 3980 | Trustees to arrange contractor | |
| Air Soiurce Heat Pump | 15500 | Electrician who moved the electicity supply would be happy to quote for this | |
| Internal Plaster Board and Skim | 10740 | Trustees to arrange contractor | |
| Saftey Grills | 10125 | Trustees to arrange contractor | |
| Eclectricals | 6250 | ||
| Plumbing (Supply and Fit) 2x wc pans, 1x Disabled pan, 3 x hand basins, 1 x Kitchen sink | 8000 | Not Required under JPSE quote | |
| Sloar Panels | 8400 | ||
| Supply and fit 102 square meters of Heavy-duty floor | 5406 | Trustees to arrange | |
| Total | £247,532,00 | ||
| Project Management (average 15%) | |||
![]()