Glyn Hall Rebuilding Project Products, Services and Costings

HIGHEST, LOWEST, AND TOTAL UK PRICE FOR REQUIRED PRODUCTS AND SERVICES

These prices are a result of research into the UK pricing market for building construction and are factual. The document shows the highest and lowest prices that could be found using conventional research methods. The areas or quantities have been included, and the totals are for both the highest and lowest prices. This section of the document only covers building materials.

The remainder of the document will show two options, ‘A’ and ‘B’. All materials and services are included in option ‘A’, and this reflects the total cost to completion. In option ‘B’, which uses an alternate contractor for the steel construction, they are removed when deemed not required. The totals also represent these omissions. These prices are not fixed and will change in either direction when quotes or local research are applied. The object is to give the reader a realistic picture of what the total finished building will cost.

What is required, how much do we need, and what will it cost for each product?

Products - Services - QuantitiesLowestHighest
Part Wall Agreement £770£5000
Demolition £8000£12000
Heras Safety Fencing £783£783
HSE Portaloo - per week£30£70
Soil Pipe 15mt,3 sealed gullys, 3 pan connections£6150£9300
Site office per week for second hand shipping container 20ft x 8ft£35£55
Provide drawings for building control and building regulations £3600£8000
Building Control Fees £900£1200
Supply and fit - 0.9mt x 0.6mt x Trench filled footing 900mm deep x 600mm wide x 29mt length, Volume: 29m × 0.9m × 0.6m = 15.66m³ Estimated Cost: Approximately per linear metre, - totalling £4,350–£7,250£4350£7250
Supply and fit – and Beam concrete floor 102 square meters, Estimated Cost: £200–£250 per m² - Total: £20,400–£25,500£20400£25000
Provide Light Guage Steel building frame to wrapped stage£66278£95000
Supply and fit - 68 square meters of new roof with OSB board, roofing felt, tile battens and metal roof tiles, Estimated Cost: £120–£230 per m².£8160£15640
Supply and fit - Brick Cladding 134 square meters, Estimated Cost: £35–£100 per m² .£4690£13040
Supply and fit - Timber Cladding 134 square meters, Estimated Cost: £30–£70 per m².£4020£9380
Supply and fit 34 mts of PVC gutter and 24 mts of downpipe. Price per meter for gutter £35-£45. Price per meter for down pipe £35-£45 per meter.£2380£3060
Supply and fit - 30 square meters of Aluminium Double Glazing, Estimated Cost: £500–£650 per m².
£15000£19000
Supply and fit – sanitary ware for Men’s, Ladies and disabled toilets and kitchen sink with water heater, kitchen unit and work top. £2325£4450
Supply and Fit – Air Source heat pump and radiators (Floor area 102 square meters, Estimated Cost: £11,000–£20,000 before grants. Government Grant: Up to £7,500 available through the Boiler Upgrade Scheme (This won’t apply, but there could be a charity angle) - Total After Grant: £3,500–£12,500£3500£12500
Supply and fit – 15 1mt x 1mt safety grilles for windows. £7500£12750
Supply and Fit 420 m2 of foil backed polyurethane insulation board at 100mm thickness: Total.£16800£21000
Supply and fit 85 m2 of Cement Screed at 50mm £1530£2295
Electrical Installation Costs Using a 3-bedroom house as a model Average Cost: Approximately £6,255. Typical Range: Between £4,450 and £8,000,£6255£8000
Plumbing Installation Costs Using a 3-bedroom house with two bathrooms as a model Average Cost: Approximately £19,000. Typical Range: Between £17,000 and £21,000, influenced by factors like fixture quality and property layout.£17000£21000
Supply and fit 358 Square meters of Plasterboard and plaster skim £25–£45 per m2£8950£16110
Supply and fit 102 square meters of Heavy-duty floor covering costs between £20 and £60 per square meter.£2040£6120
Decorating with undercoat, gloss, and emulsion.£3000£6000

The table below shows Option ‘A’. This shows everything that would be required from start to finish assuming that we handed the whole project over to someone to manage the construction on our behalf.

Option A
ProductLowestHighestAverage
Party Wall Agreement/Award77050003620
LGS Construction, including design900009500092500
Building Control Services (Mark)126612661266
Drawings for Building Control and Building Regulations360080005800
Heras Safety Fencing 784784784
Site office80001200010000
Demolition80001200010000
Portaloo per week307050
Soil Pipe 15mt,3 sealed gulleys, 3 pan connections615093007725
Supply and fit 102 square meters of Heavy-duty floor
Footings435072505800
Sub Floor204002550022950
Cement Screed st 50mm thickness153022951933
Scaffolding (Erection)537089507160
Scaffolding (on going hire over 12 months)390078005850
Roofing81601564011900
Guttering and Downpipes238030602720
Brick Cladding4690134009045
Polyurethane Foil Backed insulation board at 100mm thickness168002100018900
Timber Cladding402093806700
Aluminium Double Glazing150001950017250
Saniary ware (Ladies, Mens, Disabled)650095008000
Supply + Fit 12 window boards, 5 internal doors, 5 sets of door furniture, 100mt of 150mm x 18mm skirting board289050703980
Air Soiurce Heat Pump110002000015500
Internal Plaster Board and Skim89501253010740
Saftey Grills75001275010125
Eclectricals450080006250
Plumbing (Supply and Fit) 2x wc pans, 1x Disabled pan, 3 x hand basins, 1 x Kitchen sink650095008000
Sloar Panels700098008400
Total£263,202,00£371,995,00£317,734,00
Project Management (average 15%)305055084240673
Total including Project Mangement£293,707,00£422,837,00£358,407,00

This table shows Option ‘B’. By changing the contractor for the LGS structure has resulted in a number of the services being amalgamated into the new quote and this has had a significant a significant impact on the overall cost

Option B
ProductAverageNOTES
Party Wall Agreement/Award3620Maybe required, maybe a local agreement can be obtained.
JPSE66278Quote Received
Building Control Services (Mark)1266Quote received
Drawings for Building Control and Building Regulations5800Trustees to arrange
Heras Safety Fencing784From Internet Search
Site officeSite Office.(Asgard Secure Steel Shed). This building is recomended by the Police.
Demolition10000Contractor on hold
Portaloo per week50Quote Requested
Soil Pipe 15mt,3 sealed gulleys, 3 pan connections7725Trustees to arrange
FootingsNot reqd for main structure. JPSE construct from inside
Sub FloorRequired for timber cladding, guttering ect
Cement Screed st 50mm thickness1933Scaffold maybe supplied by roofing contractor within quote. If not, may require addition rental for externals
Scaffolding (Erection)7160Trustees to arrange contractor
Roofing11900Trustees to arrange contractor
Guttering and Downpipes2720Trustees to arrange contractor
Brick Cladding9045Trustees to arrange contractor
Polyurethane Foil Backed insulation board at 100mm thickness18900Trustees to arrange contractor
Timber Cladding6700Trustees to arrange contractor
Aluminium Double Glazing17250Trustees to arrange contractor
Saniary ware (Ladies, Mens, Disabled)8000Trustees to arrange contractor
Supply + Fit 12 window boards, 5 internal doors, 5 sets of door furniture, 100mt of 150mm x 18mm skirting board3980Trustees to arrange contractor
Air Soiurce Heat Pump15500Electrician who moved the electicity supply would be happy to quote for this
Internal Plaster Board and Skim10740Trustees to arrange contractor
Saftey Grills10125Trustees to arrange contractor
Eclectricals6250
Plumbing (Supply and Fit) 2x wc pans, 1x Disabled pan, 3 x hand basins, 1 x Kitchen sink8000Not Required under JPSE quote
Sloar Panels8400
Supply and fit 102 square meters of Heavy-duty floor5406Trustees to arrange
Total£247,532,00
Project Management (average 15%)

Loading